 Create a JIRA Project with Scrum template and Name it College Hostel

Create an epic for Managing the Hostel and name it as Hostel Room Management

Create 2 user stories in the above epic ( Top 1 to 10 floors, Arrange Beds for each room) and assign to a user.

Create 2 subtasks in "Top 1 to 10 floors" user story 

      1. Arrange each room equipment

      2. Test all the utilities

Create 2 subtasks in "Arrange Beds for each room" 

      1. Arrange single Bed

      2. Arrange Matteress.


Create a sprint for both tasks and change the status form To Do to progress and once the work is completed then it should be "Done"

Check the Backlogs and Boards for each activity.





1 comments:

Pong said...

pong


Select "scrum" > Select a team-managed project > Name "College Hostel" > create project

Select create > Issue Type "Epic" > Summary "Hostel Room Management" > Assign to self > Description "To manage a Hostel Room"
> Labels "Hostel" > Issue "Hostel Room Management" > Create

Create > Story > Summary "Top 1 to 10 floors" > Assign to self > Labels "Hostel" > Linked Issue "blocks" > Issue "Hostel Room Management" > create

Create > Story > Summary "Arrange Beds" > Assign to self > Labels "Hostel" > Linked Issue "blocks" > Issue "Hostel Room Management" > create

Select "CH-2" > create child issue > "Arrange each room equipment" > create > select "in progress"

Select "CH-2" > create child issue > Test all the utilities > create > select "in progress"


Select "CH-3" > create child issue > "Arrange single bed" > create > select "in progress"

Select "CH-3" > create child issue > "Arrange mattresses" > create > select "in progress"

Select tasks > drag into CH-sprint > Start sprint > check tasks are done > Select "complete"